Project:

Major Healthcare Provider

Location:

Eagan and Chaska, MN

Customer Profile:

Large provider of healthcare services moves from a co-location facility to an owned facility.

Overview:

  • 1 year planning process
  • 7 month implementation
  • 8 weekend moves
  • Average move: 250 servers per move group
  • Largest Move: 389 servers
  • Average of 35 technicians per move group
  • Managing 6 trucks per move group
  • Average of 420 technician hours per move
  • Average of 40 hours of Project Management time per move group
  • Custom Crates to improve efficiency and safety of the asset moving
  • Over 10,000 data center assets moved since 2002

“Parallel is an integral part of our move process, we couldn’t have done it without you.”
– Storage Manager

For the past 10 years, Parallel Technologies has developed process and the specialty that has enabled our company to execute on our most successful server migration ever. Our unique capabilities, which combines our technical and logistical services, are unmatched by our competition. Our competencies have earned the confidence of the client and the manufactures to move HP, Dell, IBM, Hitachi, Net App and Cisco where due to manufacture support contracts the manufactures may void the warrantees